Featured Image

Phase III Projects & Status Updates

Phase III of our Capital Improvement Bond is scheduled to begin in April 2021. As projects begin, develop and are completed, we will update the status of the project. Statuses in RED indicate that the project is not completed or is in progress. Statuses in GREEN indicate the project has been completed.

Pictures of select projects will be posted in the photo gallery below as they unfold. Check back frequently for updates to see the progress and different states of projects.

Current Status: Planning
Last Updated: Tuesday, January 26, 2021

Comsewogue High School

  • Interior Renovations of 2 Art Rooms

  • Install Carbon Monoxide Detectors

  • Parking Lot, Sidewalk and Curb Replacement 

  • Repair CMU Cracks

  • New Pressbox, Toilet and Concession Stand (Phase 3B)

JFK Middle School

  • Install Carbon Monoxide Detectors

  • Parking Lot, Sidewalk and Curb Replacement

  • Brickwork

  • Masonry Repairs & Add Stainless Steel Cap at Chimney 

  • Replace Classroom Ceilings & Lighting

  • Replace Waterless Urinals and Sinks

  • Replace Perimeter Chain Link Fence Along Terryville Road

Boyle Road Elementary School

  • Interior Renovation of Art Room

  • Install Carbon Monoxide Detectors

  • Replace Caulk and Tuck-point Brick

  • Masonry Repairs & Add Stainless Steel Cap & Chimney

  • Re-caulk Windows and Sills

  • Upgrade Electrical Service

  • Repair Interior CMU Cracks

  • Replace Stage and Cafeteria Sound System

  • Interior Renovation of Art Room

Terryville Road Elementary School

  • Interior Renovation of Art Room

  • Install Carbon Monoxide Detectors

  • Upgrade Electrical Service

  • Repair CMU Cracks 

  • Replace Main Office Rooftop Air Conditioning

  • Replace Domestic Hot Water Heater

  • Add Solar Panels to Roof (On Hold)

Clinton Avenue Elementary School

  • Install Carbon Monoxide Detectors

  • Add Receptacles to Classrooms and Hallways

  • Replace caulk and tuck-point brickwork

  • Masonry Repairs & Add Stainless Steel Cap at Chimney

  • Reset and Caulk Stone Sills

  • Replace Window Caulking

  • Repair CMU Cracks

  • Tie remaining Fans to Day/Night System 

Norwood Avenue Elementary School

  • Install Carbon Monoxide Detectors  

  • Add Gym, Cafeteria and District Office Board Room to BMS 

  • Replace Roof Above District Office