Bond Status Updates - Summer 2019

Below are the statuses of the Bond Projects taking place in Summer 2019. As projects begin, develop and are completed, we will update the status of the project. Pictures of projects as they unfold will be posted in the photo gallery below. Check back frequently for updates!

Last Updated: Tuesday, July 9, 2019

Comsewogue High School

  • Kitchen Ceiling Replacement: DEMO COMPLETE, RECONSTRUCTION IN PROGRESS

  • Security Vestibule: IN PROGRESS

  • Cafeteria Ceiling: IN PROGRESS

  • Interior Doors Locksets to Meet ADA Compliance: IN PROGRESS

JFK Middle School

  • Security Vestibule: IN PROGRESS

  • Kitchen Ceiling Replacement: IN PROGRESS

  • Interior Doors Locksets to Meet ADA Compliance: IN PROGRESS

  • Skylight Protection and Replacement: IN PROGRESS

Boyle Road Elementary School

  • Parking Lot and Sidewalk Replacement: DEMO COMPLETE, RECONSTRUCTION IN PROGRESS

  • Security Vestibule: IN PROGRESS

  • Interior Doors Locksets to Meet ADA Compliance: IN PROGRESS

  • Ventilation Upgrades for Music Rooms: IN PROGRESS

  • Gas Conversion and Cooled Condenser: IN PROGRESS

Terryville Road Elementary School

  • Cafeteria Floor Replacement: OLD FLOOR REMOVED, NEW FLOOR INSTALL WEEK OF JULY 8TH

  • Parking Lot and Sidewalk Replacement: DEMO COMPLETE, RECONSTRUCTION IN PROGRESS

  • Security Vestibule: IN PROGRESS

  • Interior Doors Locksets to Meet ADA Compliance: IN PROGRESS

  • Kitchen Walk-In Cooler: IN PROGRESS

Clinton Avenue Elementary School

  • Security Vestibule: IN PROGRESS

  • Interior Doors Locksets to Meet ADA Compliance: IN PROGRESS

  • Gas Conversion and Cooled Condenser: IN PROGRESS

  • Kitchen Ceiling Replacement: DEMO COMPLETE, RECONSTRUCTION IN PROGRESS

Norwood Avenue Elementary School

  • Security Vestibule: IN PROGRESS

  • Interior Doors Locksets to Meet ADA Compliance: IN PROGRESS

  • Kitchen Ceiling Replacement: IN PROGRESS

  • Kitchen Serving Line Reconfiguration: IN PROGRESS