Phase I Project List

Phase I Status: Under Construction


Comsewogue High School

  • Installation of Security Vestibule

  • Replace corridor locksets for higher security / to meet ADA Compliance

  • Replace Kitchen Ceiling

  • Remove door hold-open devices and replace (12 Interior Doors)

  • Replace Cafeteria Ceiling and Lighting

  • Re-balance and upgrade Main Office Duct work and Controls

Total Cost of Projects at Comsewogue High School: $836,250

JFK Middle School

  • Replace front Entry and Construct Security Vestibule

  • Replace corridor locksets for higher security / to meet ADA Compliance

  • Replace Kitchen Ceiling

  • Add missing closers to Corridor Doors

  • Provide Fresh Air Intake in Rooms 205A, 103 and 224

  • Replace Exterior Doors and Frames

  • Replace 1 Skylight; Add Fall Protection to all skylights

Total Cost of Projects at JFK Middle School: $963,650

Boyle Road Elementary School

  • Installation of Security Vestibule

  • Gas Conversion for Kitchen

  • Replace water-cooled refrigeration condenser with air

  • Replace and add door closers on 10 doors throughout the building

  • Repair vandalized rooftop penthouse and provide guards

  • Provide district-wide portable lift for stage access

  • Replace Corridor Knob locksets for higher security / to meet ADA Compliance

  • Provide booster pump for Kindergarten Wing

  • Sidewalk Replacement

  • Parking Lot Replacement

Total Cost of Projects at Boyle Road Elementary School: $1,213,435

Terryville Road Elementary School

  • Installation of Security Vestibule

  • Replace corridor locksets for higher security / to meet ADA Compliance

  • Replace and add door closers allowance for 10 doors

  • Provide Fresh Air Intake for 2 Stage Heating & Ventilation Units

  • Sidewalk Repair and Replacement

  • Parking Lot Replacement

  • Remove and Replace Walk-In Cooler in Kitchen

  • Replace Cafeteria Floor (Asbestos Abatement)

Total Cost of Projects at Terryville Road Elementary School: $1,520,000

Clinton Avenue Elementary School

  • Installation of Security Vestibule

  • Replace Kitchen Ceiling

  • Replace and Add 10 Door Closers

  • Provide Fresh Air Intake for Old Bookroom

  • Replace Corridor Knob locksets for higher security / to meet ADA Compliance

  • Replace 6 exterior doors and frames

  • Replace water-cooled condenser

  • Gas Conversion in Kitchen

Total Cost of Projects at Clinton Avenue Elementary School: $656,000

Norwood Avenue Elementary School

  • Installation of Security Vestibule

  • Replace Kitchen Ceiling

  • Door Replacements

  • Add Closers to all Corridor Doors

  • Provide Fresh Air Intake for Primary Project Room and 2 Speech Rooms

  • Reconfiguration of the Kitchen Serving Line

  • Replace corridor locksets for higher security / to meet ADA Compliance

Total Cost of Projects at Norwood Avenue Elementary School: $620,615