Phase II Projects & Status Updates

Below are the statuses of the Phase II Bond Projects, which began in Spring 2020. As projects begin, develop and are completed, we will update the status of the project. Statuses in RED indicate that the project is not completed or is in progress. Statuses in GREEN indicate the project has been completed.

Pictures of select projects will be posted in the photo gallery below as they unfold. Check back frequently for updates to see the progress and different states of projects.

Current Status: Completed
Last Updated: Friday, April 16, 2021

Comsewogue High School

  • Renovation of Faculty Bathrooms and Nurse's Bathrooms to Meet ADA Compliance: COMPLETED

  • Replace Cafeteria Windows, Storefront and Tech Room Windows: COMPLETED

  • Replace Waterless Urinals and Sinks: COMPLETED

  • Add Remaining RUT and HVAC Units to BMS: COMPLETED

  • Install Batting Cage for Upper Gym: COMPLETED

  • Expansion of Project Adventure Elements: COMPLETED

  • Brickwork: COMPLETED

  • Masonry Repairs & Add Stainless Steel Cap at Chimney: COMPLETED

JFK Middle School

  • Renovate Faculty Bathrooms to Meet ADA Compliance: COMPLETED

  • Reconnect leaders to pools at recess area: COMPLETED

  • Add Electrical Circuits for Air Conditioning: COMPLETED

  • Replace Auditorium Seating: COMPLETED

  • Replace Carpet in Auditorium: COMPLETED

  • Provide a Permanent Sound System in Auditorium: COMPLETED

  • Repair CMU: COMPLETED

  • Replace Hallway Ceilings: COMPLETED

  • Provide infill at Railing in Boiler Room: COMPLETED

Boyle Road Elementary School

  • Renovate Faculty Bathrooms to Meet ADA Compliance: COMPLETED

  • Provide additional Exterior Lighting: COMPLETED

  • Replace all Waterless Urinals and Sinks: COMPLETED

  • Repair and Replace Drainage in 1 Boys Bathroom: COMPLETED

  • Regrade back pitch at South and Southwest: COMPLETED

  • Provide infill mesh at Boiler Room Railing: COMPLETED

  • Add Circuits to Cafeteria, Kitchen and Gym Area: COMPLETED

  • Replace 3 Exterior Light Poles: COMPLETED

  • Replace Railings and Tread Nosings at Loading Dock Stairs: COMPLETED

  • Repair Crack at Retaining Wall: COMPLETED

  • Add 2 Pole-Mounted Lights and Structures in South Parking Lot: COMPLETED

Terryville Road Elementary School

  • Renovate Faculty Bathrooms to Meet ADA Compliance: COMPLETED

  • Add Circuits for Air Conditioning Units: COMPLETED

  • Brickwork: COMPLETED

  • Tuck-point Chimney: COMPLETED

  • Roof Replacement: COMPLETED

  • Add Boiler Room to Generator: COMPLETED

  • Add Drainage at Rear Drive: COMPLETED

  • Add Spare Electrical Panels: COMPLETED

  • Replacement of PA/Intercom System: COMPLETED

  • Replace Waterless Urinals and Sinks: COMPLETED

Clinton Avenue Elementary School

  • Renovate Faculty Bathrooms to Meet ADA Compliance: COMPLETED

  • Repair and Replace Asphalt / Mill Top Course of Asphalt: COMPLETED

  • Repair and Add Exterior Lighting in Rear of Building: COMPLETED

  • Replace Waterless Urinals and Sinks: COMPLETED

  • Replace Sidewalks: COMPLETED

  • Provide infill mesh at Boiler Room Railing: COMPLETED

  • Replace Student Wardrobes / Storage Units: COMPLETED

Norwood Avenue Elementary School

  • Replace Elevator Controls and Hydraulics: COMPLETED

  • Renovate Faculty Bathrooms to Meet ADA Compliance: COMPLETED

  • Repairs to Parking Lot: COMPLETED

  • Replace Asphalt at District Office Parking Lot: COMPLETED

  • Add Additional Parking for Pre-K Program: COMPLETED

  • Replace Sidewalks: COMPLETED

  • Install additional Electrical Outlets in Classrooms: COMPLETED

  • Repair Roof Drain: COMPLETED

  • Replace Waterless Urinals and Sinks: COMPLETED

  • Repair Loading Dock: COMPLETED

  • Replace Student Wardrobes / Storage Units: COMPLETED

  • Brickwork: COMPLETED

  • Masonry Repairs & Add Stainless Steel Cap at Chimney: COMPLETED

  • Repair CMU Cracks: COMPLETED