Phase III of our Capital Improvement Bond is nearing completion. As projects begin, develop and are completed, we will update the status of the project. Statuses in RED indicate that the project is not completed or is on hold. Statuses in BLUE indicate that the project is in progress. Statuses in GREEN indicate the project has been completed.

Pictures of select projects will be posted in the photo gallery below as they unfold. Check back frequently for updates to see the progress and different states of projects.

Current Status:Completed
Last Updated: Wednesday, July 26, 2023

Comsewogue High School

  • Interior Renovations of 2 Art Rooms: COMPLETED

  • Install Carbon Monoxide Detectors: COMPLETED

  • Parking Lot, Sidewalk and Curb Replacement: COMPLETED

  • Repair CMU Cracks: COMPLETED

  • New Field House (Press Box, Bathrooms and Concession Stand): COMPLETED

JFK Middle School

  • Install Carbon Monoxide Detectors: COMPLETED

  • Parking Lot, Sidewalk and Curb Replacement: COMPLETED

  • Brickwork: COMPLETED

  • Masonry Repairs & Add Stainless Steel Cap at Chimney: COMPLETED

  • Replace Classroom and Lobby Ceilings & Lighting: COMPLETED

  • Replace Waterless Urinals and Sinks: COMPLETED

  • Replace Perimeter Chain Link Fence Along Terryville Road: COMPLETED

Boyle Road Elementary School

  • Interior Renovation of Art Room: COMPLETED

  • Install Carbon Monoxide Detectors: COMPLETED

  • Replace Caulk and Tuck-point Brick: COMPLETED

  • Masonry Repairs & Add Stainless Steel Cap & Chimney: COMPLETED

  • Re-caulk Windows and Sills: COMPLETED

  • Upgrade Electrical Service: COMPLETED

  • Repair Interior CMU Cracks: COMPLETED

  • Replace Stage and Cafeteria Sound System: COMPLETED

Terryville Road Elementary School

  • Interior Renovation of Art Room: COMPLETED

  • Install Carbon Monoxide Detectors: COMPLETED

  • Upgrade Electrical Service: COMPLETED

  • Repair CMU Cracks: COMPLETED

  • Replace Main Office Rooftop Air Conditioning: COMPLETED

  • Replace Domestic Hot Water Heater: COMPLETED

  • Add Solar Panels to Roof: COMPLETED

Clinton Avenue Elementary School

  • Install Carbon Monoxide Detectors: COMPLETED

  • Add Receptacles to Classrooms and Hallways: COMPLETED

  • Replace caulk and tuck-point brickwork: COMPLETED

  • Masonry Repairs & Add Stainless Steel Cap at Chimney: COMPLETED

  • Reset and Caulk Stone Sills: COMPLETED

  • Replace Window Caulking: COMPLETED

  • Repair CMU Cracks: COMPLETED

Norwood Avenue Elementary School

  • Install Carbon Monoxide Detectors: COMPLETED

  • Replace Roof Above District Office: COMPLETED